How to Order a Custom Roll Forming Machine: Step-by-Step Process
RollForm Team · 2026-10-22 · Tags: order-process, custom, buying-guide
Ordering a custom roll forming machine doesn’t have to be complicated.
This guide walks you through the typical process when you work with a Chinese manufacturer like ZT RollForm Machine.
Step 1: Send your profile drawing
The more information you provide, the more accurate the quote:
- Profile drawing (DWG, DXF, PDF, or even a hand sketch)
- Material type and thickness range (e.g. galvanized steel 1.0–2.0 mm)
- Required production speed (meters per minute)
- Coil inner diameter and max coil weight
- Output length tolerance and cut-off method (flying cut or post-cut)
- Your local voltage and phase (e.g. 380V 50Hz 3-phase, 220V 60Hz single-phase)
Tip: If you have a sample profile, ship it to the factory. Physical samples prevent 90% of misunderstandings.
Step 2: Technical proposal & quotation
Within 2–3 working days, you’ll receive:
- A machine layout drawing showing decoiler, roll former, cutter, runout table
- A list of main components (brand of PLC, VFD, bearings, hydraulic pump)
- FOB price, lead time, payment terms (typically 30% T/T deposit + 70% before shipment)
- Warranty terms (standard 12 months after commissioning)
Step 3: Design confirmation
After you accept the quote:
- The engineering team produces detailed assembly drawings
- You review and sign off on the design
- Any modifications are made before manufacturing starts
Step 4: Manufacturing (30–45 days)
Typical production timeline:
| Week | Activity |
|---|---|
| 1–2 | Material preparation, cutting, welding frame |
| 3–4 | Machining roll shafts, gearbox assembly |
| 5–6 | Roll tool design & CNC machining |
| 7 | Electrical wiring, PLC programming |
| 8 | Factory test run with your sample material |
Step 5: Factory Acceptance Test (FAT)
Before shipping:
- The factory runs the machine with your sample steel coil
- You receive video and photos of the test run
- You can send your own technician or hire a third-party inspector (like SGS)
Step 6: Shipping & installation
- The machine is loaded in a 40HQ container (standard line size)
- Installation manual, electrical schematic, and operation video are included
- Remote video guidance is provided for commissioning
- On-site installation support available on request
What to ask before you sign
- What’s included in the price? (decoiler, runout table, tooling spares?)
- How long does tooling changes take? (quick-change cassettes vs. manual)
- Do you provide English operation manuals?
- What’s the response time for spare parts?
- Can you customize the control panel to our language?
Typical lead time summary
| Machine type | Lead time |
|---|---|
| Standard C/Z purlin line | 30–35 days |
| Custom roof sheet line | 35–45 days |
| Double-layer combined line | 40–50 days |
| Fully automatic with stacker | 50–60 days |